The projects listed below refer to projects with a total estimated investment scheduled in the five-year investment plan that is expected to be developed for implementation periods 2016 and 2017.
All these projects are emblematic for the current administration of President Juan Carlos Varela, due to its high social impact for the country, helping to improve the quality of life of thousands of Panamanians and to the economic development in different areas of the country.
-
REHABILITATION AND EXTENSION OF THE BRUJAS AVENUE AND ANDREWS BLVD. (PANAMA PACIFIC AVENUE)
PROJECT TYPE: ROAD
Projected Bidding Date: June, 2016 (1st Stage).
Projected Work Starting Date: October, 2016 (1st Stage).
Projected Work Finish Date: August, 2017 (1st Stage).
-
CONSTRUCTION OF FIRST PHASE OF THE NEW WASTEWATER TREATMENT PLANT AND REHABILITATION OF PUMPING STATIONS
PROJECT TYPE: WASTEWATER TREATMENT PLANT
Projected Bidding Date: March, 2017.
Projected Work Starting Date: July, 2017.
Projected Work Finish Date: January, 2019
-
CONSTRUCTION OF THE MAIN LINE OF DRIVING OF DRINKING WATER AND STORAGE TANK FOR THE TOWN CENTER OF THE AREA
PROJECT TYPE: DRINKING WATER SUPPLY.
Projected Bidding Date: March, 2016.
Projected Work Starting Date: June, 2016.
Projected Work Finish Date: June, 2018